Forging Plant Expansion & Additions

International Crankshaft needed extra space in their facility to meet growing production demands. Denham-Blythe was able to design and build an expansion that involved planning and zoning work, relocation of a city street, and seven separate building additions on three sides of the existing facility without disrupting plant operations.

  • Managed a 12-phased schedule
  • Placed process foundations for induction heater, stamping press, twister press, coining press, bolster wash, and cullet conveyor
  • Erected a water cooling system
  • Constructed a waste water treatment system
  • Greatly expanded the existing parking lot
  • Installed storm water runoff controls

  • Contract Amount
  • $18,900,000
  • Location
  • Georgetown, Kentucky
  • Square Feet
  • 87,000
  • Duration
  • 24 Months
  • Project Type
  • Expansion & Additions