Automotive

Toyotetsu America

Supplier of structural automotive components

Stamping & Welding Facility Additions

Toyotetsu aimed to greatly increase their production by installing ten new presses. Denham-Blythe provided design-build services to efficiently construct an involved program of press pits, scrap tunnels, utilitity trenches, and clean out pits.

  • Erected a conventional steel structure based on spacious 65'x65' bays
  • Built two 85' clear span bays employing 20-ton overhead cranes
  • Placed 10 press foundations - largest being 2000-ton press resting in 20' deep pit bearing on caisson foundation system
  • Constructed scrap loading docks
  • Created side-loading shipping area
  • Included a new break room for each of three working zones

  • Contract Amount
  • $19,400,000
  • Location
  • Somerset, Kentucky
  • Square Feet
  • 314,000
  • Duration
  • 25 Months
  • Project Type
  • Additions